All Collections
Palmetto Service Areas & Market Resources
Michigan
Michigan - Lansing Board of Water & Light - Contract Received Confirmed (CRC) Checklist
Michigan - Lansing Board of Water & Light - Contract Received Confirmed (CRC) Checklist
Andrew - LR Product Expert avatar
Written by Andrew - LR Product Expert
Updated over a week ago
mceclip0.png

Document Name

Doc. Type

Who Signs?

Notes

Loan Documents

E-signature

System Owner(s)

- Follow financier guidelines (client on the title, legal name used, etc)

- Must be clear of any financier stipulations, if applicable

HIC (Homeowners Installation Contract)

E-signature

System Owner(s)

The name matches the loan exactly.

Utility Bill

Upload

N/A

All pages required.

HOA Questionnaire

E-Signature

System Owner

Palmetto is not responsible for HOA recourse against clients if they answer "no" on this form.

Virtual Site Survey (VSS) Submitted

- Can be completed by rep or homeowner

- Completed in full with clear photos

- Click here for a full sales VSS guide

Lansing Solar Rebate Application

E-signature

Utility Bill Holder

Rebate Application only. Interconnection Application and REC Agreement are sent from the utility to the customer before install.

mceclip1.png

Document Name

Doc. Type

Who Signs?

Notes

HIC (Installation Agreement)

E-signature

System Owner(s)

Utility Bill

Upload

N/A

All pages required. A recent copy (within 2 months) is required.

HOA Questionnaire

E-Signature

System Owner(s)

Palmetto is not responsible for HOA recourse against clients if they answer "no" on this form.

Virtual Site Survey (VSS) Submitted

- Can be completed by rep or homeowner

- Completed in full with clear photos

- Click here for a full sales VSS guide

Lansing Solar Rebate Application

E-signature

Utility Bill Holder

Rebate Application only. Interconnection Application and REC Agreement are sent from the utility to the customer before install.