We are smashing our current install timeline guarantees! Palmetto is building confidence in the industry with our Install Timeline Guarantee. Our investments in sales, installation, and customer experience are paying off - we’re exceeding our timeline guarantees, or you get a rebate on the installation. With Palmetto, you’ll get paid sooner and enjoy excellent customer service.
Applicable Markets with Guarantees
Service Area | Install Timeline Guarantee | Current Average |
Greater Charlotte - Western | 65d | 50d |
Dallas - Fort Worth Metro | 65d | 56d |
Western South Carolina | 65d | 60d |
Greater Las Vegas | 50d | 34d |
Columbus - Central Ohio | 75d | 37d |
Greater Orlando - Tampa - Central | 65d | 42d |
Atlanta Metro | 65d | 47d |
Western Pennsylvania | 75d | 47d |
Central Massachusetts | 120d | 65d |
Boston Metro | 120d | 67d |
Houston Metro | 60d | 36d |
Rhode Island | 90d | 45d |
These markets also have great install timelines! (guarantee not yet launched)
Service Area/Market | Current Average |
Upstate South Carolina | 35d |
NC Triangle - Raleigh - Greensboro | 42d |
Wilmington - Eastern NC - Coastal OBX | 43d |
Cleveland - Akron - NE Ohio | 45d |
Greater Columbia - Midlands SC | 45d |
Greater Charlotte | 50d |
Southwest GA | 51d |
Central GA | 63d |
Eastern PA | 63d |
Cincinnati - Dayton - SW | 67d |
Things to know about the guarantee
The timeline guarantee applies starting once a final proposal has been submitted as an order. Orders must have completed site approval/site survey, all closing documents signed, and any necessary change orders completed. The timeline guarantee is defined from the date of final order submitted to the date of installation complete.
Timeline guarantees do not apply to projects with these situations, which may create unforeseen delays:
Pre-construction work (re-roofs, electrical upgrades)
Customers with an HOA
Customer requested design changes post-sale
Change Order response timeline from the partner > than 48 hrs
Any change order driven by the customer after the final proposal is executed and submitted for fulfillment